[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256271":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256271,840,1,"单选题","工程施工顺序应在满足工程建设的要求下，组织分期分批施工。同时应遵循（ ）的原则进行安排。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先地上、后地下",false,{"key":16,"text":17,"correct":18},"B","先主体、后附属",true,{"key":20,"text":21,"correct":14},"C","先附属、后主体",{"key":23,"text":24,"correct":14},"D","先支线、后干线","工程施工顺序应在满足工程建设的要求下，组织分期分批施工。同时应遵循先主体、后附属的原则进行安排。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]