[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256270,840,1,"单选题","现场施工准备工作中的“三通一平”是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A水通、电通、路通、场地平整",true,{"key":16,"text":17,"correct":18},"B","水通、路通、网通、路面平整",false,{"key":20,"text":21,"correct":18},"C","水通、路通、电话通、场地平整",{"key":23,"text":24,"correct":18},"D","水通、电通、网通、路面平整","现场施工准备工作中的“三通一平”是指水通、电通、路通、场地平整",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]