[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256266,840,1,"单选题","竣工验收阶段主要进行的工作有：①组织现场验收，②编制竣工验收计划，③办理交工手续，④进行竣工结算，⑤移交竣工资料，⑥竣工验收准备。工作先后排序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑥②①④⑤③",true,{"key":16,"text":17,"correct":18},"B","⑥②①③④⑤",false,{"key":20,"text":21,"correct":18},"C","②⑥①③④⑤",{"key":23,"text":24,"correct":18},"D","②⑥①④③⑤","竣工验收阶段主要进行的工作有：竣工验收准备；编制竣工验收计划；组织现场验收；进行竣工结算；移交竣工资料；办理交工手续",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]