[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256261,840,1,"单选题","GCL的施工流程正确的是",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基底检验→吊运就位→搭接宽度调整→人工铺展→搭接处撒彭润粉→进行后续施工",false,{"key":16,"text":17,"correct":14},"B","基底检验→吊运就位→人工铺展→搭接处撒彭润粉→搭接宽度调整→进行后续施工",{"key":19,"text":20,"correct":14},"C","基底检验→吊运就位→搭接宽度调整→搭接处撒彭润粉→人工铺展→进行后续施工",{"key":22,"text":23,"correct":24},"D","基底检验→吊运就位→人工铺展→搭接宽度调整→搭接处撒彭润粉→进行后续施工",true,"GCL的施工流程：基底检验→吊运就位→人工铺展→搭接宽度调整→搭接处撒彭润粉→进行后续施工。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]