[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256227,840,1,"单选题","现浇预应力钢筋混凝土连续梁钢筋骨架的施焊顺序，宜由骨架的（ ）进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","中间到两边，对称地向两端",true,{"key":16,"text":17,"correct":18},"B","中间到两边，不对称地向两端",false,{"key":20,"text":21,"correct":18},"C","两边到中间，对称地",{"key":23,"text":24,"correct":18},"D","两边到中间，不对称地","“现浇预应力钢筋混凝土连续梁钢筋骨架的施焊顺序，宜由骨架的中间到两边，对称地向两端进行。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]