[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256189":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256189,840,1,"单选题","预应力混凝土连续梁悬臂浇筑施工中，顶板纵向预应力筋正确的张拉顺序是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","上下对称张拉",false,{"key":16,"text":17,"correct":14},"B","左右对称张拉",{"key":19,"text":20,"correct":14},"C","上下、左右依次张拉，",{"key":22,"text":23,"correct":24},"D","上下、左右对称张拉",true,"预应力混凝土连续粱悬臂浇筑施工中，顶板、腹板纵向预应力筋的张拉顺序一般为上下、左右对称张拉，设计有要求时按设计要求施做。顸应力混凝土连续梁合龙顺序一般是先边跨、后次跨、再中跨。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]