[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256170,840,1,"单选题","施工成本管理的基本流程正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本预测→管理决策→管理计划→过程控制→成本核算→分析和考核",true,{"key":16,"text":17,"correct":18},"B","成本预测→管理计划→管理决策→过程控制→成本核算→分析和考核",false,{"key":20,"text":21,"correct":18},"C","成本核算→成本预測→管理决策→管理计划→过程控制→分析和考核",{"key":23,"text":24,"correct":18},"D","成本核算→成本预测→管理决策→管理计划→过程控制→分析和考核","施工成本管理的基本流程正确的是：成本预测→管理决策→管理计划→过程控制→成本核算→分析和考核。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]