[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256168,840,1,"单选题","沉人桩施工中，沉桩时终止锤击的控制是以（ ）为主.",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","桩的人土深度",false,{"key":16,"text":17,"correct":14},"B","贯入度",{"key":19,"text":20,"correct":14},"C","锤击力",{"key":22,"text":23,"correct":24},"D","桩端设计标高",true,"常用的沉入桩有钢筋混凝土桩、预应力混凝土管桩和钢管桩.沉入桩施工技术要点中，终止锤击的控制应以控制桩端设计高程为主，贯入度为辅.",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]