[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256158,840,1,"单选题","箱涵顶进施工流程中，顶进设备安装的紧后工艺流程是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","既有线加固",true,{"key":16,"text":17,"correct":18},"B","箱涵试顶",false,{"key":20,"text":21,"correct":18},"C","吃土顶进",{"key":23,"text":24,"correct":18},"D","监控量测","箱涵顶进施工的工艺流程：现场调查一工程降水一工作坑开挖一后背制作一滑板制作一铺设润滑隔离层一箱涵制作一顶进设备安装一既有线加固一箱涵试项一吃土项进一监控量测一箱体就位一拆除加固设施一拆除后背及顶进设备一工作坑恢复。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]