[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256150,840,1,"单选题","关于石方路基施工要点，下列说法错误的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先修筑试验段，以确定松铺厚度、压实机具组合、压实遍数及沉降差等施工参数",false,{"key":16,"text":17,"correct":18},"B","修筑填石路堤应进行地表清理，先码砌中部，然后逐层水平填筑石料，确保边坡稳定",true,{"key":20,"text":21,"correct":14},"C","填石路堤宜选用12t以上的振动压路机",{"key":23,"text":24,"correct":14},"D","路基范围内管线、构筑物四周的沟槽宜回填土料","石方路基的施工要点：（1）修筑填石路堤应进行地表清理，先码砌边部，然后逐层水平填筑石料，确保边坡稳定。（2）先修筑试验段，以确定松铺厚度、压实机具组合、压实遍数及沉降差等施工参数。（3）填石路堤宜选用12t以上的振动压路机、25t以上轮胎压路机或2.5t的夯锤压（夯）实。（4）路基范围内管线、构筑物四周的沟槽宜回填土料。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]