[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256148,840,1,"单选题","沟槽的支撑应在管道两侧及管顶以上0．5m回填完毕并压实后，在保证安全的情况下进行拆除，并应采用（ ）填实缝隙。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","细砂",true,{"key":16,"text":17,"correct":18},"B","级配砂石",false,{"key":20,"text":21,"correct":18},"C","灰土",{"key":23,"text":24,"correct":18},"D","冻土","沟槽的支撑应在管道两侧及管顶以上o．5rn回填完毕并压实后，在保证安全的情况下进行拆除，并应采用细砂填实缝隙。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]