[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256139,840,1,"单选题","清孔后的沉渣厚度应符合设计要求。设计未规定时，摩擦桩的沉渣厚度不应大于（ ）mm；端承桩的沉渣厚度不应大于（ ）mm。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","500；200",false,{"key":16,"text":17,"correct":14},"B","400；200",{"key":19,"text":20,"correct":14},"C","400；100",{"key":22,"text":23,"correct":24},"D","300；100",true,"清孔后的沉渣厚度应符合设计要求。设计未规定时，摩擦桩的沉渣厚度不应大于300mm；端承桩的沉渣厚度不应大于100mm。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]