[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256138,840,1,"单选题","某公司计划编制施工组织设计，已收集和熟悉了相关资料，调查了项目特点和施工条件，计算了主要工种的工程量，确定了施工的总体部署，接下来应进行的工作是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟定施工方案",true,{"key":16,"text":17,"correct":18},"B","编制总进度计划",false,{"key":20,"text":21,"correct":18},"C","编制资源需求计划",{"key":23,"text":24,"correct":18},"D","编制施工准备工作计划","已收集和熟悉了相关资料，调查了项目特点和施工条件，计算了主要工种的工程量，确定了施工的总体部署，接下来应进行的工作是拟定施工方案",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]