[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256131,840,1,"单选题","下列关于悬臂浇筑混凝土连续梁合龙的说法中，错误的是",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合龙顺序一般是先边跨，后次跨，再中跨",false,{"key":16,"text":17,"correct":14},"B","合龙段长度宜为2m",{"key":19,"text":20,"correct":14},"C","合龙宜在一天中气温最低时进行",{"key":22,"text":23,"correct":24},"D","梁跨体系转换时，支座反力的调整应以变形控制为主",true,"选项D应为：粱跨体系转换时，支座反力的调整应以高程控制为主，反力作为校核.",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]