[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256119,840,1,"单选题","围堰使用期间河流的常水位为+2．Om，可能出现的最高水位（包括浪高）为+3.Om，则该围堰顶的最低标高应为（ ）m。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2.5",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","3.5",true,{"key":23,"text":24,"correct":14},"D","4","本题考点涉及围堰施工的一般规定。围堰高度应高出施工期间可能出现的最高水位（包括浪高）0．5~0．7m。题干中给出了已知条件：围堰使用期间河流可能出现的最高水位（包括浪高）为+3.0m，则该围堰顶的最低标高应为十3.0+0.5=+3.5m。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]