[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256115,840,1,"单选题","盖梁支架和脚手架的地基处理应按施工组织设计要求进行，一般采取先用压路机碾压，人工整平后，再在土基上铺设（ ）碎石，然后铺设150mm混凝土的方法处理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50mm",false,{"key":16,"text":17,"correct":18},"B","100mm",true,{"key":20,"text":21,"correct":14},"C","150mm",{"key":23,"text":24,"correct":14},"D","200mm","盖梁支架和脚手架的地基处理应按施工组织设计要求进行，一般采取先用压路机碾压，人工整平后，再在土基上铺设枕木或路基箱板作为支架基础的方法，或在土基上铺设100mm碎石，然后铺设150mm混凝土的方法处理。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]