[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256113,840,1,"单选题","下列有关水池施工降、排水要求说法不正确的是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","选择可靠的降低水位方法，严格进行降水施工，对降水所用机具随时做好保养维护，并有备用机具",false,{"key":16,"text":17,"correct":18},"B","在施工过程中要间断性的降排水，并应对降、排水系统进行检查和维护",true,{"key":20,"text":21,"correct":14},"C","降、排水应输送至抽水影响半径范围以外的河道或排水管道，并防止环境水源进入施工基坑",{"key":23,"text":24,"correct":14},"D","基坑承受压水影响时，应进行承压水降压的影响进行评估","在施工过程中不得间断性的降排水，并应对降、排水系统进行检查和维护。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]