[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256097,840,1,"单选题","下列哪种方法不属于施工成本目标控制的方法（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人工费的控制",false,{"key":16,"text":17,"correct":14},"B","材料费的控制",{"key":19,"text":20,"correct":21},"C","加班时间的控制",true,{"key":23,"text":24,"correct":14},"D","施工机械使用费的控制","施工阶段是控制建设工程项目成本发生的主要阶段,它通过确定成本目标并按计划成本进行施工资源配置,对施工现场发生的各种成本费用进行有效控制,方法如下:一，人工费的控制二，材料费的控制三，施工机械使用费控制四，施工分包费用的控制",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]