[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256096,840,1,"单选题","预应力筋张拉后，应及时进行孔道压浆，多跨连续有连接器的预应力筋孔道，应张拉完一段灌注一段；孔道压浆宜采用水泥浆，水泥浆应符合设计要求，如设计无要求，则不能低于（ ）MPa。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":21},"C","30",true,{"key":23,"text":24,"correct":14},"D","40","预麻力籂张托后，府及时进行孔道压浆，多跨连续有连接器的预应力筋孔道，应张拉完一段灌注一段；孔道压浆宜采用水泥浆，水泥浆应符合设计要求，如设计无要求，则不能低于30MPa。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]