[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256082,840,1,"单选题","下列雨期道路工程施工质量保证措施中，属于面层施工要求的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当天挖完、填完、压完，不留后患",false,{"key":16,"text":17,"correct":14},"B","应按2%-3%横坡整平压实，以防积水",{"key":19,"text":20,"correct":14},"C","未碾压的料层受雨淋后，应进行测试分析，按配合比要求重新搅拌",{"key":22,"text":23,"correct":24},"D","及时浇筑、振动、抹面成型、养护",true,"本题考点涉及道路雨期施工质量控制要求。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]