[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1256078,840,1,"单选题","施工计划调度包括：项目部成立施工调度组织、监督检查计划执行情况；定期召开施工现场调度会（例会）解决存在问题，检查落实会议决议；（ ）负责编写施工日志。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目负责人",false,{"key":16,"text":17,"correct":14},"B","技术负责人",{"key":19,"text":20,"correct":14},"C","施工员",{"key":22,"text":23,"correct":24},"D","专人",true,"施工日志也叫施工日记，是在建筑工程整个施工阶段的施工组织管理、施工技术等有关施工活动和现场情况变化的真实的综合性记录，也是处理施工问题的备忘录和总结施工管理经验的基本素材，是工程交竣工验收资料的重要组成部分。施工日志可按单位、分部工程或施工工区（班组）建立，由专人负责收集、填写记录、保管。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]