[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256057,840,1,"单选题","下列不属于竣工图基本要求的是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工测量应以工程施工中有效的测量控制网点为依据进行测量.控制点被破坏时，应在保证测细部点的精确度下进行恢复",true,{"key":16,"text":17,"correct":18},"B","市政公用工程竣工图应包括与施工（及设计变更）相对应的全部图纸及根据工程竣工情况需要补充的图纸",false,{"key":20,"text":21,"correct":18},"C","各专业竣工图应符合规范标准以及合同文件规定",{"key":23,"text":24,"correct":18},"D","竣工总图汇编完成后，应经原设计及施工单位技术负责人审核、会签","竣工图基本要求包括三点：（1）市政公用工程竣工图应包括与施工（及设计变更）相对应的全部图纸及根据工程竣工情况需要补充的图纸；（2）各专业竣工图应符合规范标准以及合同文件规定；（3）竣工总图汇编完成后，应经原设计及施工单位技术负责人审核、会签。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]