[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256050":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256050,840,1,"单选题","混凝土板养生时间应根据混凝土强度增长情况而定，一般宜为（ ）d。养生期满方可将覆盖物清除，板面不得留有痕迹。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7~14",false,{"key":16,"text":17,"correct":14},"B","7~21",{"key":19,"text":20,"correct":21},"C","14~21",true,{"key":23,"text":24,"correct":14},"D","14~28","混凝土板养生时间应根据混凝土强度增长情况而定，一般宜为14~21d。养生期满方可将覆盖物清除，板面不得留有痕迹。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]