[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256030,840,1,"单选题","城镇道路应在春末和夏季组织施工，施工期的最低气温应在（ ）以上。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5℃",true,{"key":16,"text":17,"correct":18},"B","10℃",false,{"key":20,"text":21,"correct":18},"C","15℃",{"key":23,"text":24,"correct":18},"D","20℃","城镇道路应在春末和夏季组织施工，施工期的最低气温应在5℃以上。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]