[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256019,840,1,"单选题","为确保桩头浮浆层凿除后桩基面混凝土达到设计强度，灌注桩的桩顶应高出设计标高（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.2～0.6m",false,{"key":16,"text":17,"correct":14},"B","0.3～0.8m",{"key":19,"text":20,"correct":21},"C","0.5～1m",true,{"key":23,"text":24,"correct":14},"D","0.8～1.5m","桩顶混凝土浇筑完成后应高出设计高程0.5～1m，确保桩头浮浆层凿除后桩基面混凝土达到设计强度。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]