[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256014":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1256014,840,1,"单选题","采用沉人桩施工时，要求在一个墩、台桩基中，同一水平面内桩接头（不是采用法兰盘接头）数不超过桩基总数的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1\u002F10",false,{"key":16,"text":17,"correct":18},"B","1\u002F4",true,{"key":20,"text":21,"correct":14},"C","1\u002F7",{"key":23,"text":24,"correct":14},"D","1\u002F2","在一个墩、台桩基中，同一水平面内桩接头数不得超过桩基总数的1\u002F4，但采用法兰盘按等强度设计的接头，可不受此限制。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]