[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1256011,840,1,"单选题","管棚施工工艺流程正确的是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","侧放孔位&rarr;钻机就位&rarr;水平钻孔&rarr;压入钢管&rarr;注浆&rarr;封口&rarr;开挖",true,{"key":16,"text":17,"correct":18},"B","钻机就位→侧放孔位→压人钢管→水平钻孔→注浆→封口→开挖",false,{"key":20,"text":21,"correct":18},"C","侧放孔位&rarr;钻机就位&rarr;水平钻孔&rarr;压入钢管&rarr;注浆&rarr;开挖&rarr;封口",{"key":23,"text":24,"correct":18},"D","钻机就位&rarr;侧放孔位&rarr;水平钻孔&rarr;压入钢管&rarr;注浆&rarr;开挖&rarr;封口","管棚施工工艺流程：侧放孔位&rarr;钻机就位&rarr;水平钻孔&rarr;压入钢管&rarr;注浆&rarr;封口斗开挖。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]