[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1256000":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1256000,840,1,"单选题","施工现场主要技术管理内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目部技术管理的岗位职责、权利义务与利益分配",false,{"key":16,"text":17,"correct":14},"B","编制、执行施工组织设计、施工方案、专项方案和作业指导书",{"key":19,"text":20,"correct":21},"C","编制、执行成本控制方案和节约保证措施",true,{"key":23,"text":24,"correct":14},"D","项目施工技术咨询和方案论证","施工现场主要技术管理内容有：项目部技术管理的岗位职责、权利义务与利益分配；贯彻执行有关法律法规和合同技术规定、技术标准；编制、执行施工组织设计、施工方案、专项方案和作业指导书；编制、执行质量控制计划、质量验收标准，进行全过程的质量管理；编制、执行安全专项方案和安全技术保证措施等",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)专业管理实务 岗位知识","建筑工程",0]