[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255916":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1255916,839,3,"判断题","市政管网工程量计算，需要试压、吹扫的管道，长度未满20m者，以20m计算；超过20m者，按实际长度计算。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"需要试压、吹扫的管道长度未满10m者，以10m计算，超过10m者按实际长度计算。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)基础知识","建筑工程",0]