[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255887":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1255887,839,3,"判断题","项目目标控制中所用的技术措施有两大类，一类是硬技术，即管理技术；一类是软技术，即工艺技术。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"项目目标控制中所用的措施有两大类，一类是硬技术，即工艺技术；一类是软技术即管理技术。",{"id":6,"name":21,"category":22,"favorite":23},"(市政施工)基础知识","建筑工程",0]