[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255529":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255529,839,2,"多选题","下列关于土石方运输计算正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","推土机的运距按挖填方区的重心之间的直线距离计算",true,{"key":16,"text":17,"correct":18},"B","铲运机运距按循环运距的三分之一",false,{"key":20,"text":21,"correct":18},"C","铲运机运距按挖方区至弃土区重心之间的直线距离",{"key":23,"text":24,"correct":14},"D","铲运机运距按挖方区至弃土区重心之间的直线距离，另加转向运距45m",{"key":26,"text":27,"correct":14},"E","自卸汽车运距按循环路线的二分之一距离计算","ADE","推土机的运距按挖填方区的重心之间的直线距离计算；铲运机运距按循环运距的二分之一或挖方区至弃土区重心之间的直线距离，另加转向运距45m；自卸汽车运距按挖方区重心至弃土区重心之间的实际行驶距离计算或按循环路线的二分之一距离计算。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]