[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255521":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255521,839,2,"多选题","某市政项目的独立土方工程，招标文件中估计工程量为100万m3，甲乙合同中约定；土方工程单价为6元\u002Fm3，当实际工程量超过估计工程量20％时，调整单价，单价调为4元\u002Fm3。工程结束时核算实际完成土方工程量为130万m3。 若因分部分项工程量清单漏项或非承包人原因引起的工程变更，造成增加新的工程量清单项目时，其对应的综合单价应按（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同中已有适用的综合单价，按合同中已有的综合单价确定",true,{"key":16,"text":17,"correct":18},"B","合同中已有适用的综合单价，按合同中类似的综合单价确定",false,{"key":20,"text":21,"correct":18},"C","合同中有类似的综合单价，按合同中已有的综合单价确定",{"key":23,"text":24,"correct":18},"D","合同中有适用或类似的综合单价，由承包人提出综合单价，经发包人确认后执行",{"key":26,"text":27,"correct":14},"E","合同中没有适用或类似的综合单价，由承包人提出综合单价，经发包人确认后执行","AE","合同中已有适用的综合单价，按合同中已有的综合单价确定；合同中没有适用或类似的综合单价，由承包人提出综合单价，经发包人确认后执行。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]