[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255518":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255518,839,2,"多选题","下列说法正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钢筋混凝土方桩、板桩按桩长度乘以桩横断面面积计算",true,{"key":16,"text":17,"correct":18},"B","钢筋混凝土管桩按桩长度乘以桩横断面面积",false,{"key":20,"text":21,"correct":14},"C","钢筋混凝土管桩按桩长度乘以桩横断面面积，减去空心部分体积计算",{"key":23,"text":24,"correct":14},"D","现浇混凝土工程量以实体积计算，不扣除钢筋、铁丝、铁件等所占体积",{"key":26,"text":27,"correct":14},"E","预制混凝土计算中空心板梁的堵头板体积不计入工程量内","ACDE","钢筋混凝土方桩、板桩按桩长度乘以桩横断面面积计算；钢筋混凝土管桩按桩长度乘以桩横断面面积，减去空心部分体积计算；现浇混凝土工程量以实体积计算，不扣除钢筋、铁丝、铁件等所占体积；预制混凝土计算中空心板梁的堵头板体积不计入工程量内。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]