[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255508":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255508,839,2,"多选题","施工项目资源管理主要是对项目所需的（ ）进行的计划、组织、指挥、协调和控制活动。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","人力",true,{"key":16,"text":17,"correct":14},"B","材料",{"key":19,"text":20,"correct":14},"C","机械设备",{"key":22,"text":23,"correct":14},"D","技术",{"key":25,"text":26,"correct":27},"E","临时设施",false,"ABCD","资源管理是对项目所需人力、材料、机械设备、技术、资金和基础设施所进行的计划、组织、指挥、协调和控制等活动。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]