[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255494":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255494,839,2,"多选题","下列关于水泥粉煤灰碎石桩的说法中，表述正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","桩机就位，调整钻杆与地面垂直，偏差不大于1.0%",true,{"key":16,"text":17,"correct":14},"B","质量检验主要分为复合地基承载力和装机完整性，一般在成桩28d后进行",{"key":19,"text":20,"correct":21},"C","一般采用长螺旋钻机干成孔。桩顶高程一般高出设计高程80cm",false,{"key":23,"text":24,"correct":14},"D","一般采用长螺旋钻机干成孔",{"key":26,"text":27,"correct":21},"E","试验数量宜为总桩数的0.5%，且没检验批不少于2根","ABD","桩机就位，调整钻杆与地面垂直，偏差不大于1.0%。一般采用长螺旋钻机干成孔。桩顶高程一般高出设计高程50cm。浇筑完成，严格按工艺设计的顺序移动钻机，进行下一根桩的施工。质量检验主要分为复合地基承载力和装机完整性，一般在成桩28d后进行，试验数量宜为总桩数的0.2%，且没检验批不少于3根。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]