[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255490":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255490,839,2,"多选题","下列关于沉井施工方法的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","挖土层应一次性进行；对于有底梁或支撑梁沉井，其相邻阁仓高差不宜超过0.5m",false,{"key":16,"text":17,"correct":18},"B","机械设备的配备应满足沉井下沉以及水中开挖、出土等要求，运行正常；废弃土方、泥浆专门处置，不得随意排放",true,{"key":20,"text":21,"correct":18},"C","下沉应平稳、均衡、缓慢，发生偏斜应通过调整开挖顺序和方式“随叫随到、动中纠偏”",{"key":23,"text":24,"correct":18},"D","干封底保持施工水平稳定地下水位距坑底不小于0.5m；在沉井封底前应用大石块将刃脚下垫实",{"key":26,"text":27,"correct":14},"E","水下混凝土封底的浇筑顺序，应从低处开始，逐渐向中心缩小","BCD","挖土层应分层、均匀、对称进行；对于有底梁或支撑梁沉井，其相邻阁仓高差不宜超过0.5m。机械设备的配备应满足沉井下沉以及水中开挖、出土等要求，运行正常；废弃土方、泥浆专门处置，不得随意排放。下沉应平稳、均衡、缓慢，发生偏斜应通过调整开挖顺序和方式“随叫随到、动中纠偏”。干封底保持施工水平稳定地下水位距坑底不小于0.5m；在沉井封底前应用大石块将刃脚下垫实。水下混凝土封底的浇筑顺序，应从低处开始，逐渐向周围扩大。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]