[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255489":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255489,839,2,"多选题","下列关于GCL垫质量控制要点的说法中，表述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","填埋区基底检验合格后方可进行GCL垫铺设作业，每一工作面施工前均要对基底进行修整和检验",true,{"key":16,"text":17,"correct":18},"B","对铺开的GCL垫进行调整，调整搭接宽度，控制在450±50mm范围内，拉平GCL垫，确保无褶皱、无悬空现象，与基础层贴实",false,{"key":20,"text":21,"correct":14},"C","掀开搭接处上层GCL垫，在搭接处均匀撒膨润土粉，将两层垫间密封然后将掀开的GCL垫铺回",{"key":23,"text":24,"correct":14},"D","根据填埋区基底设计坡向，GCL垫的搭接，尽量采用顺坡搭接，即采用上压下的搭接方式；注意避免出现十字搭接，而尽量采用品形分布",{"key":26,"text":27,"correct":14},"E","GCL垫需当日铺设当日覆盖，遇有雨雪天气停止施工，并将已铺设的GCL垫覆盖好","ACDE","填埋区基底检验合格后方可进行GCL垫铺设作业，每一工作面施工前均要对基底进行修整和检验。对铺开的GCL垫进行调整，调整搭接宽度，控制在250±50mm范围内，拉平GCL垫，确保无褶皱、无悬空现象，与基础层贴实。掀开搭接处上层GCL垫，在搭接处均匀撒膨润土粉，将两层垫间密封然后将掀开的GCL垫铺回。根据填埋区基底设计坡向，GCL垫的搭接，尽量采用顺坡搭接，即采用上压下的搭接方式；注意避免出现十字搭接，而尽量采用品形分布。GCL垫需当日铺设当日覆盖，遇有雨雪天气停止施工，并将已铺设的GCL垫覆盖好。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]