[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255476":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255476,839,2,"多选题","下列关于盾构法隧道施工的说法中，表述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","盾构工作井的宽度一般比盾构直径小1.6～2.0m",false,{"key":16,"text":17,"correct":18},"B","盾构始发指盾构自始发工作井内盾构基座上开始推进到完成初始段掘进止",true,{"key":20,"text":21,"correct":18},"C","盾构机盾尾进入洞口后，拼装整环临时管片（负一环），并在开口部安装上部轴向支承，使随后盾构掘进时全部盾构千斤顶都可使用",{"key":23,"text":24,"correct":18},"D","盾构接收是指自掘进距接收工作井一定距离到盾构机落到接收工作井接收基座上止",{"key":26,"text":27,"correct":18},"E","盾构机推进结束后，应迅速拼装管片成环。管片拼装完成后，随着盾构的推进，管片与洞体之间出现空隙","BCDE","盾构工作井的宽度一般比盾构直径大1.6～2.0m，以满足操作空间要求。盾构始发指盾构自始发工作井内盾构基座上开始推进到完成初始段（通常50～100m）掘进止，亦可划分：洞口土体加固段掘进、初始掘进两个阶段。盾构机盾尾进入洞口后，拼装整环临时管片（负一环），并在开口部安装上部轴向支承，使随后盾构掘进时全部盾构千斤顶都可使用。盾构接收是指自掘进距接收工作井一定距离（通常100m左右）到盾构机落到接收工作井接收基座上止。盾构机推进结束后，应迅速拼装管片成环。管片拼装完成后，随着盾构的推进，管片与洞体之间出现空隙。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]