[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255472":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255472,839,2,"多选题","下列关于门窗工程施工工艺的说法中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","电热张拉顺序可由池壁底端开始，逐环向上",false,{"key":16,"text":17,"correct":18},"B","每一环预应力筋应对称张拉，并不得间断",true,{"key":20,"text":21,"correct":14},"C","必须重复张拉时，同一根钢筋的重复次数不得超过5次，发生裂纹时，应更换预应力筋",{"key":23,"text":24,"correct":18},"D","一般条件下，喷射保护层厚50mm，喷射作业宜在气温高于15℃时施工",{"key":26,"text":27,"correct":14},"E","在喷射保护层凝结后，应加遮盖、保持湿润不应小于28d","BD","电热张拉顺序可由池壁顶端开始，逐环向下。每一环预应力筋应对称张拉，并不得间断。必须重复张拉时，同一根钢筋的重复次数不得超过3次，发生裂纹时，应更换预应力筋。一般条件下，喷射保护层厚50mm，喷射作业宜在气温高于15℃时施工。在喷射保护层凝结后，应加遮盖、保持湿润不应小于14d。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]