[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255462":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255462,839,2,"多选题","某连续梁桥全长179m，拟采用悬臂浇筑法施工，挂篮的主桁部分采用三角形结构，行走为整体移动，其余采用竹胶板。其施工程序计划如下：①在墩顶托架上浇筑0号块并实施墩梁临时固结系统。②在0号块上安装悬臂挂篮，向两侧依次对称地分段浇筑主梁至合龙段。③在临时支架或梁端与边墩向临时托架上支模板浇筑现浇梁段。④主梁合龙段可在改装的简支挂篮托架上浇筑。 施工单位在合龙阶段拟采用下列措施，其中符合规范要求的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合龙段的长度宜为1m",false,{"key":16,"text":17,"correct":18},"B","宜在一天中气温最低时进行",true,{"key":20,"text":21,"correct":18},"C","合龙前，在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除",{"key":23,"text":24,"correct":18},"D","合龙段的混凝土强度宜提高一级，以尽早施加预压力",{"key":26,"text":27,"correct":18},"E","连续梁的梁跨体系转换，应在合龙段及全部纵向连续预应力筋张拉、压浆完成，并解除各墩临时固结后进行","BCDE","施工单位在合龙阶段拟应采用：宜在一天中气温最低时进行；合龙前，在两端悬臂预加压重，并于浇筑混凝土过程中逐步撤除；合龙段的混凝土强度宜提高一级，以尽早施加预压力和连续梁的梁跨体系转换，应在合龙段及全部纵向连续预应力筋张拉、压浆完成，并解除各墩临时固结后进行",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]