[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255432":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255432,839,2,"多选题","下列关于人工挖孔灌注桩的说法中，表述正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","挖掘顺序应为相邻的孔同时开挖",false,{"key":16,"text":17,"correct":18},"B","开挖时一般组织连续作业应采用电动链滑车或架设三脚架，用10～20kN慢速卷扬机提升",true,{"key":20,"text":21,"correct":14},"C","桩孔挖掘、支撑护壁必须间隔作业，不得连续",{"key":23,"text":24,"correct":18},"D","在季节融化层融化的夏季，一般不宜采用挖孔桩",{"key":26,"text":27,"correct":18},"E","井口周围需用木料、型钢或混凝土制成框架或围圈予以保护，井口围护应高于地面20～30cm，以防止图、石、杂物滚入孔内伤人","BDE","挖掘顺序视土质基桩孔布置而定，一般不得在相邻两孔同时开挖，当同一承台有多根桩基，应对角、间隔开挖。开挖时一般组织连续作业应采用电动链滑车或架设三脚架，用10～20kN慢速卷扬机提升。桩孔挖掘、支撑护壁必须连续作业，不得中间停顿。在季节融化层融化的夏季，一般不宜采用挖孔桩。井口周围需用木料、型钢或混凝土制成框架或围圈予以保护，井口围护应高于地面20～30cm，以防止图、石、杂物滚入孔内伤人。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]