[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255428":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255428,839,2,"多选题","下列换填法施工要点正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不得直接使用泥炭、淤泥、淤泥质土和有机质土进行换填",true,{"key":16,"text":17,"correct":14},"B","分段施工时，不得在基础、墙角下接缝",{"key":19,"text":20,"correct":21},"C","高炉干渣垫层大面积施工宜采用平碾、振动碾或羊足碾分层碾压，每层松铺厚度宜不大于350mm",false,{"key":23,"text":24,"correct":14},"D","压实度一般采用环刀法、灌砂法等方法检验",{"key":26,"text":27,"correct":21},"E","对砂石、高炉干渣等的压实度试验一般采用环刀法、灌砂法","ABD","不得直接使用泥炭、淤泥、淤泥质土和有机质土进行换填，土中易溶盐不得超过允许值，不得使用液限大于50%、塑性指数大于26的细粒土。分段施工时，不得在基础、墙角下接缝。高炉干渣垫层大面积施工宜采用压路机、振动压路机分层碾压，每层松铺厚度宜不大于350mm。压实度一般采用环刀法、灌砂法等方法检验。对砂石、高炉干渣等的压实度试验一般采用灌砂法。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]