[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255425":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255425,839,2,"多选题","土方路基施工中，路基压实应（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先轻后重",true,{"key":16,"text":17,"correct":18},"B","先重后轻",false,{"key":20,"text":21,"correct":18},"C","先快后慢",{"key":23,"text":24,"correct":14},"D","先慢后快",{"key":26,"text":27,"correct":14},"E","均匀一致","ADE","土方路基施工中，压实时应做到先轻后重、先慢后快、均匀一致。；压实前应先检查土壤含水量，使其在最佳含水量附近士2%时进行碾压；压路机轮外缘距路基边应不小于0.5m的保持安全距离，压实度应达到要且表面应无显著轮迹、翻浆、起皮、波浪等现象等",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]