[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255407":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255407,839,2,"多选题","下列关于强夯法施工要点中，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","降水联合低能级强夯法处理地基时必须设置合理的降排水体系，包括降水系统和排水系统",true,{"key":16,"text":17,"correct":14},"B","低能级强夯应采用“少击多遍，先轻后重”的原则进行施工，施工时据临近建筑物由近向远夯击",{"key":19,"text":20,"correct":21},"C","当地下水位距地表3m以下且表层为非饱和土时，可直接进行夯击",false,{"key":23,"text":24,"correct":21},"D","抽真空设备一套设备有效控制面积一般为600～800m㎡",{"key":26,"text":27,"correct":14},"E","强夯振动的安全距离一般为10～15m，强夯置换施工按由内向外、隔行跳打的原则完成全部夯点得施工","ABE","降水联合低能级强夯法处理地基时必须设置合理的降排水体系，包括降水系统和排水系统。低能级强夯应采用“少击多遍，先轻后重”的原则进行施工。当地下水位距地表2m以下且表层为非饱和土时，可直接进行夯击。强夯振动的安全距离一般为10～15m。强夯置换施工按由内向外、隔行跳打的原则完成全部夯点得施工。施工时据临近建筑物由近向远夯击。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]