[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255399":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255399,839,2,"多选题","下列堆载预压法施工要点说法正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","袋装砂井和塑料排水带施工所用钢管内径略小于两者尺寸",false,{"key":16,"text":17,"correct":14},"B","砂袋会塑料排水带应高出砂垫层不少于80mm",{"key":19,"text":20,"correct":14},"C","预压区中心部位的砂垫层底标高应低于周边的砂垫层底标高，以利于排水",{"key":22,"text":23,"correct":24},"D","堆载预压施工，应根据设计要求分级逐渐加载",true,{"key":26,"text":27,"correct":24},"E","竖向变形量每天不宜超过10～15mm，水平位移每天不宜超过4～7mm","DE","袋装砂井和塑料排水带施工所用钢管内径略大于两者尺寸。砂袋会塑料排水带应高出砂垫层不少于100mm。预压区中心部位的砂垫层底标高应高于周边的砂垫层底标高，以利于排水。堆载预压施工，应根据设计要求分级逐渐加载，在加载过程中应每天进行竖向变形量、水平位移及孔隙水压力等项目的检测，且根据监测资料控制加载速率。竖向变形量每天不宜超过10～15mm，水平位移每天不宜超过4～7mm。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]