[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255267":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1255267,839,2,"多选题","施工控制桩的测量方法主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","平行线法",true,{"key":16,"text":17,"correct":18},"B","垂直线法",false,{"key":20,"text":21,"correct":14},"C","延长线法",{"key":23,"text":24,"correct":18},"D","缩短线法",{"key":26,"text":27,"correct":18},"E","任意交叉线法","AC","施工控制桩的测量由于中线在路基施工中都要被挖掉或推埋，为了在施工中能控制中线位置，应在不受施工干扰、便于引用、易于保存桩位的地方测设施工控制桩。测量方法主要有平行线法和延长线法两种，可根据实际情况相互配合使用。",{"id":6,"name":31,"category":32,"favorite":33},"(市政施工)基础知识","建筑工程",0]