[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1255179,839,1,"单选题","随着科学技术水平和管理水平的提高，社会生产力的水平也必然会提高，原有定额不能使用生产发展时，定额授权部门根据新的情况对定额进行修订和补充，这体现了定额的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","真实性",false,{"key":16,"text":17,"correct":18},"B","时效性",true,{"key":20,"text":21,"correct":14},"C","系统性",{"key":23,"text":24,"correct":14},"D","可变性","工程建设定额的稳定性是相对的。任何一种工程定额都只能是反映了一定时期的生产力水平，当技术进步了，生产力向前发展了，定额就会与已发展了的生产力不相适应，因此，在适当的时期进行定额修编就是必然的了。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]