[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1255170,839,1,"单选题","以下关于灌注桩水下混凝土工程量计算规则的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","以根计量，按设计图小数量计算",false,{"key":16,"text":17,"correct":14},"B","以立方米计算，按不同截面在桩长范围内以体积计算",{"key":19,"text":20,"correct":14},"C","以米计量，按设计图示尺寸以桩长（包括桩尖）计算",{"key":22,"text":23,"correct":24},"D","按设计桩长加上桩顶设计超灌高度乘以设计横断面面积计算，桩顶超灌高度无设计要求的，则按1m计算",true,"灌注桩水下混凝土时按设计桩长加上桩顶设计超灌高度乘以设计横断面面积计算，桩顶超灌高度无设计要求的，则按1m计算。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]