[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1255149,839,1,"单选题","下列选项中，不属于运用动态控制原理控制施工进度的步骤的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工进度目标的逐层分解",false,{"key":16,"text":17,"correct":18},"B","对施工进度目标的分析和比较",true,{"key":20,"text":21,"correct":14},"C","对施工进度目标进行动态跟踪和控制",{"key":23,"text":24,"correct":14},"D","调整施工进度目标","运用动态控制原理控制施工进度的步骤如下：1）施工进度目标的逐层分解。2）在施工过程中，对施工进度目标进行动态跟踪和控制",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]