[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1255141,839,1,"单选题","总结经验，改正缺点，并将遗留问题转人下一轮循环是PDCA中的（ ）阶段。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划",false,{"key":16,"text":17,"correct":14},"B","执行",{"key":19,"text":20,"correct":14},"C","检查",{"key":22,"text":23,"correct":24},"D","处置",true,"总结经验，改正缺点，并将遗留问题转人下一轮循环是PDCA中的处置阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]